ROADWORKS are being carried out on Taunton's newest main road over 11 weeks.

Various works are starting today (Monday, June 13) on a stretch of Trenchard Way.

Here's the full list of major roadworks starting this week as announced by Travel Somerset.

MONDAY, JUNE 13.

Trenchard Way, Taunton, various works, 55 working days.

Cothelstone Road, Bishops Lydeard, earthworks, 15 days.

Buckland Lane, Great Elm, resurfacing, 10 days.

Goose Lane and Church Lane, Chilton Polden, sewage connections, nine days.

Briscoe Lane, Wellington, various works, five days.

Homefield Close, Beckington, resurfacing, five days.

Mantle Street, Wellington, drainage repairs, two days.

Cher, Minehead, resurfacing, two days.

WEDNESDAY, MARCH 15.

Quirke Street, Minehead, resurfacing, one day.

FRIDAY, MARCH 17.

Wheathill Lane, Milborne Port, resurfacing, five days.

SATURDAY, MARCH 18.

The Avenue and Higher Kingston, Yeovil, site investigation, one day.